Power

Every weekday's Power stories from Morgan Downey's Commodity News email, newest first, with the day's what-moved line (Thu, Aug 20 to Wed, Sep 16). Open a date for the full issue across every commodity.

Wednesday, September 16, 2026Full issue →

What's moving · FERC orders all six US grid operators to justify or reform large-load tariffs for data centers, with PJM also proposing ride-through rules after July 4 GW trip.

PJM proposes ride-through rules for large data center loads
Shane Snider · TechTarget
PJM proposed new ride-through rules requiring large computational loads (data centers ≥50 MW at ≥100 kV) to stay connected during voltage/frequency disturbances instead of switching to backup generation. The rules respond to a June FERC order and a July event where nearly 4,000 MW of Northern Virginia data center load disconnected during a transmission fault. New facilities must demonstrate compliance starting November; the changes aim to reduce reliability risks from unpredictable large-load behavior. Read →
FERC orders six grid operators to justify or reform large-load tariffs
Federal Energy Regulatory Commission
FERC issued show-cause orders under Section 206 to PJM, MISO, SPP, CAISO, ISO-NE, and NYISO directing them within 60 days to justify current tariffs or propose reforms for data centers and other large loads. The orders target cost allocation, co-location rules, cost-recovery agreements, and expedited processes to speed reliable interconnections while protecting ratepayers. SPP’s existing High Impact Large Load framework is noted as a model; separate PJM co-location proceedings advance firm/non-firm contract demand transmission services. Read →

Tuesday, September 15, 2026Full issue →

What's moving · PJM files FERC backstop auction plan to fill 6.8 GW capacity shortfall driven by data-center load forecasts.

Soluna wins conditional base-load status for 100 MW ERCOT project
Soluna Holdings
ERCOT conditionally classified Soluna’s 100 MW Project Dorothy wind-powered data-center campus as base load under its Batch Zero large-load interconnection process. The classification follows a similar approval for the company’s 166 MW Project Kati and preserves interconnection capacity while exempting the project from further reliability evaluation in the study. An additional 50 MW request at the site is already under separate study; the status is conditional on ERCOT’s ongoing verification process. Read →

Monday, September 14, 2026Full issue →

What's moving · PJM 2028/29 capacity auction cleared at $325/MW-day cap amid data-center-driven shortfall; ERCOT audits 400+ data-center projects in Batch Zero.

ERCOT real-time hub prices average $30/MWh overnight Sep 13.
ERCOT
ERCOT real-time settlement point prices across hubs and load zones averaged around $30/MWh in the early overnight hours of September 13, 2026, with minor fluctuations between roughly $27/MWh and $33/MWh. No scarcity alerts or price spikes were reported, reflecting normal grid conditions with adequate reserves. This provides a baseline for weekend power pricing in Texas amid ongoing large-load interconnection reviews. Read →
French EPEX day-ahead prices turn negative midday Sep 13.
Selectra
EPEX SPOT day-ahead prices for France on September 13, 2026, reached negative territory around midday, with a low of -0.01 €/MWh at 12:00 and several hours near zero before rising to a 234 €/MWh peak at 20:00. The average settled near 130 €/MWh, down slightly from the prior day. Abundant renewable output relative to lower weekend demand drove the midday negatives, a recurring feature in European spot markets. Read →
MISO peaks at 92.9 GW with $904/MWh marginal cost Sep 13.
MISO Grid Watch (X)
MISO recorded a peak demand of 92,917 MW on September 13, 2026, at 5:15 PM ET with a minimum reserve margin of 4.1 GW and a maximum marginal cost of $903.77/MWh. The day was graded as an 'ALERT' status before closing normal. This highlights tightening conditions in the Midwest ISO during the period, though no system-wide scarcity pricing or conservation alerts were detailed in the update. Read →
Saturday, September 12, 2026 · Week in Review →

Thursday, September 10, 2026Full issue →

What's moving · PJM files FERC backstop auction plan to fill 6.8 GW data-center-driven capacity shortfall.

PJM files FERC plan for backstop auction to fill 6.8 GW shortfall
Utility Dive
PJM filed a proposal at FERC for a one-time reliability backstop auction from Sept. 30 to Oct. 21 to procure new capacity and close a 6.8 GW shortfall left by its last base residual auction. Surging data center load forecasts and lagging new supply caused the gap; the plan also enables bilateral deals between data centers and generators, with costs allocated across zones and a proposed $555/MW-day price cap. Read →
German power prices surge on wind slump to €192/MWh
Bloomberg
German day-ahead power prices on EPEX SPOT rose to the highest level since June, averaging €191.82/MWh, with the 7 p.m. hour peaking at €460.86/MWh. Forecast wind output dropping to 3.5 GW at peak hours forced greater reliance on costlier fossil fuels, tightening the market on EPEX. Read →

Wednesday, September 9, 2026Full issue →

What's moving · PJM readies 6 GW reliability backstop auction for data-center-driven shortfall as ERCOT audits 300+ large-load projects.

PJM files for 6 GW backstop auction to fix data-center shortfall.
April Bonner · Energy-Storage.news
PJM submitted a two-part FERC plan on July 31 and August 7 for a one-time Reliability Backstop Procurement auction from September 30 to October 21 targeting 6 GW to close the 2028/2029 capacity shortfall. The mechanism lets PJM procure new capacity (including BESS with siting advantages) on behalf of new large loads, with costs passed to utilities and ultimately data centers via state tariffs rather than spread to other ratepayers; large loads without their own supply will face priority curtailment in emergencies. This follows repeated capacity auctions clearing at the $325/MW-day cap while falling short of reliability targets due to data-center load growth. Read →

Tuesday, September 8, 2026Full issue →

What's moving · PJM files FERC plan for September backstop capacity auction to close 6.8 GW data-center driven shortfall.

Storm Goretti lifts Western Europe spot power prices
World Energy News
Intraday power prices across Western European markets rose Friday as Storm Goretti caused outages and generation issues. EPEX Spot data showed Germany baseload averaging €90.44/MWh and France €87.35/MWh, up from prior-day closes, with UK day-ahead rising 3.5 pounds to £87.50/MWh amid lower-than-forecast wind output and a French nuclear capacity dip. Read →

Monday, September 7, 2026Full issue →

What's moving · ERCOT day-ahead prices spike to $85/MWh evening peak on Sep 7 as heat and load test grid amid ongoing data-center audit pause.

ERCOT Sep 7 DAM prices peak at $85 evening amid heat.
ERCOT
ERCOT's day-ahead market for Sep 7 shows evening prices rising sharply to $85.22/MWh in the Houston zone and similar levels across hubs, with non-spin reserves also elevated in peak hours. This reflects tightening conditions from heat-driven demand on a grid already managing record load forecasts and a paused large-load interconnection process. The moves highlight immediate scarcity pricing risks tied to data-center and other large-load growth in Texas. Read →
ERCOT Sep 7 day-ahead prices hit $85 evening peak.
ERCOT
Settlement point prices for Sep 7 delivery show average levels around $40-50/MWh early in the day rising to $85/MWh in the evening across major hubs including Houston and North. Real-time data from prior days also indicated elevated conditions. These price signals underscore ERCOT's energy-only market responding to peak demand pressures from air conditioning and growing computational loads. Read →
ERCOT reports generation loss event on Sep 5.
ERCOT
ERCOT control room logged a sudden 654 MW generation loss on Sep 5 at 02:11, with frequency dropping to 59.959 Hz while load sat at 60,125 MW. Multiple prior days showed no comparable events. The incident adds operational stress to a system already navigating high demand periods and the state-mandated audit of hundreds of GW in data-center interconnection requests. Read →
Saturday, September 5, 2026 · Week in Review →

Friday, September 4, 2026Full issue →

What's moving · PJM files FERC plan for Sept. 30-Oct. 21 backstop auction to procure 6.8 GW at up to $555/MW-day cap amid data-center driven shortfall.

Oncor assesses Texas data center freeze impact on 300 GW pipeline
Utility Dive
Sempra executives, parent of Oncor, expressed support for Texas Gov. Abbott's data center interconnection pause during an earnings call, citing needs for durable outcomes amid public opposition, with uncertainty over timelines for Oncor's 44 GW of Batch Zero-qualified large-load projects in its territory. The pause halts ERCOT's Batch Zero review process for projects meeting new criteria, leaving Oncor's $47.5 billion capital plan excluding related spending for now. This reflects broader scrutiny of inflated load forecasts in ERCOT's 474 GW queue, where 90% are data centers, as the utility navigates alignment of load with new generation. Read →

Thursday, September 3, 2026Full issue →

What's moving · PJM issues heat alerts and DOE backup order as hot weather drives peak loads near 152 GW amid data-center demand.

Heat wave raises blackout risk on PJM, MISO grids
Reuters
Intense heat is expected to push MISO peak demand near 121 GW on Wednesday, close to its 127.1 GW record, while PJM faces similar strain across its 13-state footprint serving 67 million people. The U.S. Department of Energy authorized PJM late Tuesday to direct backup generation as a last resort before a Level 3 energy emergency alert, following PJM's Maximum Generation and Load Management alerts for Sept. 2 and a continuing Hot Weather Alert through Sept. 3. This tightens real-time conditions in the largest U.S. power market already stressed by surging data-center loads. Read →
Europe sees more negative power prices from solar
pv magazine Global / S&P Global
Negative electricity prices rose in the first half of 2026 across major European markets including EPEX SPOT zones, up about 2% from 2025 records and over 13 times 2022 levels, driven by high solar output exceeding midday demand. France saw the most negative hours due to strong nuclear baseload; Germany experienced wider spreads supporting battery economics with daily peaks above €650/MWh. The trend pressures solar PPAs and accelerates storage deployment as evening scarcity pricing intensifies from gas-fired ramping. Read →

Wednesday, September 2, 2026Full issue →

What's moving · PJM files FERC backstop auction plan to fill 6.8 GW capacity shortfall driven by data-center demand.

PJM files FERC plan for backstop auction to fill 6.8 GW shortfall
Utility Dive
PJM filed a proposal at FERC on Friday for a one-time reliability backstop auction running Sept. 30 to Oct. 21 to procure new capacity against the 6.8 GW shortfall from its prior base residual auction. The filing targets surging data-center load forecasts, with PJM estimating potential growth of up to 70 GW by 2038, and includes a bilateral contracting process that could reduce the auction target. The proposal sets a $555/MW-day price cap and would allocate costs across PJM zones. Read →
Texas freezes data center grid connections pending audit of 474 GW queue
Reuters
Texas Gov. Greg Abbott directed ERCOT and state regulators to audit all proposed data centers in the interconnection queue, halting new grid connections until verification of ownership, power use, water consumption, and incentives. Requests have surged from 48 GW in 2023 to more than 474 GW currently, with about 90% from data centers, more than five times ERCOT’s record peak demand. ERCOT delayed its Batch Zero transmission planning study in response. Read →
Data centers drove 40% of PJM capacity auction costs, per monitor
Utility Dive
Monitoring Analytics reported that data-center load forecasts accounted for $6.5 billion, or 40%, of the $16.4 billion in costs from PJM’s December capacity auction. Across the last three auctions, data-center forecasts beyond existing loads drove $21.3 billion, or 45%, of the $47.2 billion total cleared capacity cost. The monitor stated data-center growth is the primary driver of tight supply-demand conditions, high prices, and shortfalls. Read →

Tuesday, September 1, 2026Full issue →

What's moving · PJM data-center demand drives capacity shortfall, backstop auction and bilateral deals amid ERCOT interconnection pause.

Texas data-center pause risks delaying 20% of US pipeline
Utility Dive
Texas Gov. Greg Abbott ordered an audit of 474 GW of ERCOT large-load interconnection requests, 90% data centers, pausing Batch Zero study deadlines. BNEF estimates the pause affects nearly 49.8 GW of projects, or about 20% of the US data-center pipeline, with potential revenue losses up to $8 billion by Q1 2027 if extended. The audit examines power sourcing, water use and incentives, delaying new interconnections until verification completes by December. Read →
ERCOT hits new peak demand record but supply limits growth
Utility Dive
Ascend Analytics projects ERCOT peak demand could reach 120 GW by 2030, up >30% from the July 22 record, but far below ERCOT’s own forecasts due to interconnection and generation supply constraints. The large-load queue has grown >200 GW since 2024, driven by data centers and other industrials, with >80% of new loads lacking matching generation by 2030. ERCOT’s energy-only market and rising costs make scarcity pricing alone insufficient to attract needed new capacity. Read →

Monday, August 31, 2026Full issue →

What's moving · PJM issues Hot Weather Alert for Aug 31, Sept 2 as real-time prices hit $400+/MWh amid data-center load growth.

PJM issues Hot Weather Alert for Aug 31, Sept 2
PJM Interconnection
PJM issued a Hot Weather Alert for its entire region from Aug 31 through Sept 2 ahead of expected hot and humid weather. The alert directs members to defer maintenance and prepare for higher demand. This coincides with real-time LMPs showing spikes, such as BGE at $719/MWh and PJM-RTO at $401/MWh in recent hours, reflecting stress from summer peaks and large loads. Read →
Saturday, August 29, 2026 · Week in Review →

Friday, August 28, 2026Full issue →

What's moving · PJM capacity shortfall and large-load rules dominate as ERCOT audits data-center queue; European spot prices rise on weather.

Storm Goretti lifts European spot power prices
World Energy News
Storm Goretti drove higher-than-expected demand and cut wind output, pushing German EPEX baseload intraday prices to €90.44/MWh and French prices to €87.35/MWh, up from Thursday closes. UK day-ahead baseload rose £3.50 to £87.50/MWh. Lower wind and nuclear availability supported the move amid the weather event. Read →

Thursday, August 27, 2026Full issue →

What's moving · PJM data-center demand drives 6.8 GW capacity shortfall in latest auction, spurring backstop procurement plans.

PJM auction shortfall hits 6.8 GW amid data center surge.
Shane Snider · Data Center Knowledge
PJM's July Base Residual Auction procured 138,318 MW but fell 6,831 MW short of the reliability requirement for the 2028/29 delivery year. The grid operator proposed a Reliability Backstop Procurement to secure additional resources up to a $555 per MW-day cap starting Sept. 30. The shortfall stems from surging large-load demand, primarily data centers, highlighting ongoing supply constraints in the largest US grid. Read →
EIA reports June wholesale prices near yearly lows.
U.S. Energy Information Administration (EIA)
Wholesale electricity prices in June 2026 stayed near the lower end of yearly ranges across most US RTO hubs including PJM, MISO, and ERCOT. PJM showed the widest monthly price range from $36/MWh to $216/MWh. Peak demand in several markets approached or hit 12-month highs, driven by summer loads. Read →
ERCOT real-time prices hold in $30-80/MWh range overnight.
ERCOT
ERCOT real-time settlement point prices on Aug 27 ranged mostly between $35/MWh and $80/MWh in early hours with no major spikes reported. The grid managed non-spin deployments earlier but recalled resources by midnight. Demand remained elevated but stable without emergency alerts. Read →

Wednesday, August 26, 2026Full issue →

What's moving · ERCOT pauses data center interconnections for governor-ordered audit, delaying 50 GW and risking $15B in project costs.

Texas audit may delay 49.8 GW data centers, cost $15B.
Nadine Hawkins · Capacity
BNEF estimates Texas Gov. Abbott's audit of 300 data center projects in ERCOT's Batch Zero queue could delay 49.8 GW of load and impose $15 billion in costs on developers. The review, ordered Aug. 3, verifies project readiness, ownership, water use and community impact before any new connections proceed. ERCOT has paused key interconnection milestones while the audit runs through at least December, leaving the 474 GW queue, 90% data centers, stalled and raising financing and construction risks for hyperscalers. Read →

Tuesday, August 25, 2026Full issue →

What's moving · SPP declares Resource Advisories for East and West BAAs amid hot weather, high loads, and low renewables forecast starting Aug 24.

Dutch EPEX day-ahead prices jump 28% on Aug 24
Selectra
Average all-in consumer electricity price on the Dutch market reached €0.3017/kWh on Aug 24, up 28.4% from the prior day with the EPEX spot component driving the move. Prices varied hourly from a low of €0.1683/kWh at 13:00 to €0.3901/kWh at 20:00. The spike reflects tighter conditions ahead of cooler forecasts for Aug 25 that point to sharply lower prices. Read →
Western US power prices drop sharply as heat eases
S&P Global
Wholesale power prices in the Western US fell as much as $62/MWh day-over-day on Aug 25 as a heat wave exits the region. CAISO NP15 and SP15 on-peak day-ahead LMPs hit multi-month highs earlier in the week (up to $63.34/MWh) on elevated cooling demand before cooling. Pacific Northwest and Desert Southwest ICE on-peak prices also declined sharply for Aug 26 delivery. Read →

Monday, August 24, 2026Full issue →

What's moving · ERCOT pauses new data center interconnections for statewide audit amid 474 GW queue dominated by AI loads.

ERCOT targets December completion for Abbott's data center audit.
Utility Dive
ERCOT plans to finish verifying and auditing all data center projects in its interconnection queue by Dec. 10, following Gov. Greg Abbott's Aug. 3 directive. The queue holds 474 GW of requests, 90% from data centers. The audit must complete before any projects advance, delaying Batch Zero studies and potentially tightening near-term supply additions in Texas. Read →
SPP issues Resource Advisory for hot weather uncertainty through Aug. 28.
SPP
SPP declared a Resource Advisory for both East and West Balancing Authority Areas effective Aug. 24 at 10 a.m./noon CT through Aug. 28 midnight due to forecast uncertainty, potential high loads, and severe hot weather that could lower wind/solar output. Operators must use extended unit commitment timelines; no public conservation required but reliability procedures activated. Read →
Saturday, August 22, 2026 · Week in Review →

Friday, August 21, 2026Full issue →

What's moving · PJM proposes framework for data centers bringing own power amid ongoing capacity shortfalls; ERCOT pauses Batch Zero large-load reviews after Abbott audit order.

PJM proposes IRAS framework and registry for new large loads
Power Magazine
PJM filed Aug. 13 at FERC for an Interim Resource Adequacy Service (IRAS) allowing new large loads (≥50 MW peak) to connect without full capacity backing while making uncovered demand curtailable ahead of other resources during tight conditions. The filing addresses the 6,831 MW shortfall from the 2028/29 capacity auction cleared at the $325/MW-day cap and follows a July 31 backstop procurement proposal. Data-center-driven load growth underpins the moves, with PJM forecasting up to 70 GW of additional large-load demand by 2038. Read →
Texas pauses data center interconnections pending audit
Utility Dive
Gov. Greg Abbott ordered an audit of the ERCOT queue totaling 474 GW (90% data centers), prompting ERCOT to delay its Batch Zero transmission planning study for the first large-load projects under new rules. ERCOT requested good-cause exceptions from the Public Utility Commission of Texas at its Aug. 20 meeting; the pause affects energization approvals for projects ≥75 MW peak and could delay timelines for developers reassessing viability. Read →
PJM reviews ride-through standards after July data center event
Utility Dive
PJM is evaluating expanded interconnection reliability requirements including ride-through standards for computational loads after 3,800 MW of data centers tripped offline in northern Virginia on July 22 following a 230-kV line fault in Dominion’s zone. The largest such event in PJM history caused load to drop from 99,984 MW to 96,205 MW with voltage/frequency swings; operators restored balance within NERC timelines. The review aligns with broader NERC efforts on standards for these facilities. Read →

Thursday, August 20, 2026Full issue →

What's moving · MISO overtakes PJM as US's largest grid by capacity on solar surge.

MISO overtakes PJM as nation's largest grid via solar boom.
Bloomberg
BloombergNEF reports MISO, serving 45 million people across 15 Midwest states, surpassed PJM in installed electric supply capacity due to rapid solar additions in states like Ohio, Michigan, Indiana and Illinois. PJM previously led until last year. The shift comes amid rising demand from data centers and manufacturing, with solar and storage driving most new US capacity additions. Read →
← Latest daysEarlier days →